York Gymnastics Centre

Extensive refurbishment post Flood damage

Harrow Consulting Ltd were appointed to undertake floor remediation works to the York Community Gymnastics Foundation on the banks of the River Foss, York.

Harrow were appointed as Lead Consultant, including design and project management services, to undertake extensive repair and refurbishment works after the substantial flooding that affected the City of York at Christmas 2015.  Extensive strip out of water damaged equipment and building fabric was undertaken with a full refurbishment of dance studios, shower facilities, gymnastics training areas, athlete dormitories, kitchens, lecture theatres and offices.

Harrow worked in conjunction with Gymnastics Foundation stakeholders and Insurance providers to ensure that works were undertaken quickly and successfully to minimise impact to the business.

Works were successfully completed in May 2016.